Connecticut has a unique legal tool called pre-judgment attachment. It allows plaintiffs to obtain a lien against a defendant’s assets before the conclusion of a lawsuit. The attachment is meant to serve as security for the plaintiff’s claim and ensure payment if the plaintiff is ultimately successful. This mechanism offers an advantage to plaintiffs in a court action, as it puts the defendant’s assets in limbo and makes it difficult for the defendant to hide or transfer them to another location. People will often make early settlements rather than have their assets remain tied up in a lawsuit. The Connecticut attachment statutes have been around for a long time. They are a useful, established tool for creditors seeking to protect themselves in litigation.
In Connecticut, a creditor can seek an attachment in one of two ways: (a) with a court order after filing an application (or sometimes by ex parte order, without notice to the debtor), or (b) via a commercial contract that waives the debtor’s right to notice and a hearing. With the second route, there is no court order. It makes it easier for the creditor to secure its claim.
Public Act 23-201
Starting in 2024, Connecticut has stricter rules for businesses that file collection lawsuits against merchant cash advance (MCA) customers. The legislature has enacted Public Act 23-201, changing the attachment by waiver process for MCA cases. So far, a fair reading of Public Act 23-201 is that it doesn’t apply to the court-ordered kind of attachment, only to the private waiver.
As before, a Connecticut MCA agreement signed before July 1, 2024, can still use the private contract waiver attachment process. The waiver in an MCA contract allows the merchant funder to attach the merchant’s bank accounts after a default. Usually that would be when the lender serves a lawsuit. But they do not have to; they can wait until the very end of the lawsuit if they want. That the attachment process is available at any time before judgment is a big deal. If the lawsuit is taking a long time, the creditor can still get security on the debtor’s assets.
For contracts dated on or after July 1, 2024, the new Act changes the attachment process in some cases. The new law only applies if the cash advance amount (purchase price) is $250,000 or less. When figuring out the $250k threshold, start with the amount the funder gives the merchant. That is what is commonly called the “purchase price.” Cash advance agreements that are above the threshold are exempt from the new rules.
The Waiver May Still Be Usable After Litigation Commences
The Act says that the waiver can’t be enforced “upon commencing any litigation.” However, the Act never says that the waiver is unenforceable after litigation has begun. So then, when exactly does litigation “commence” under the new Act? Under Connecticut law, it is when service of process on the defendant is complete. See Broderick v. Jackman, 167 Conn. 96, 99 (1974). So the Act bars using the waiver to attach when the lawsuit begins, at service of process. But it doesn’t bar using it once service is complete. So if the lawsuit drags on, the waiver should still be good as security after litigation has started. Then the only question is whether the waiver as written actually complies with the new law.
Even with the new rules, an attachment by waiver still remains a powerful tool that funders will weigh. But for a cash advance that is $250,000 or less and signed from July 1, 2024 on, the waiver may still be usable after litigation commences.